Blog by Jane Marsh – The coordination nightmare: why Electricity, gas, and hydrogen grid planning still can’t talk to each other

A household considering a heat pump installation needs to know whether its electricity supply can support the change. Across the U.K., businesses considering alternative energy face similar uncertainty on a larger scale. Both decisions depend on infrastructure that electricity, gas and hydrogen planners still assess separately. Without a shared plan, customers must weigh upgrade costs while the networks work out how their investments fit together.

Each Network Still Plans Alone

The Scottish Government describes energy networks as currently planned separately and identifies better coordination as a priority. Electricity and gas planners, therefore, need a common view of future demand as heating and transport change. Their assumptions influence where investment goes and how much capacity each network needs.

Consider an area where households might replace gas boilers with heat pumps. Electricity planners need to anticipate additional demand, while gas planners need to assess how much heating demand their network could retain. Different assumptions about the same homes could lead to investment plans that fail to meet local needs. This illustrates why agreement on future demand matters before construction starts.

Integration means coordinating those decisions across distinct networks. The Scottish Government’s whole system planning arrangements seek to connect national priorities with regional and local needs. Shared assumptions could help planners identify where strengthening the electricity network supports the wider transition and where other infrastructure still serves an important purpose.

A Joined-Up Grid Plan Is Still Years Away

The Centralised Strategic Network Plan (CSNP) will set out the major networks needed to carry electricity alongside gas and hydrogen through 2050. Ofgem says the full plan is due in 2028, so until then, network operators must make investment decisions using interim electricity plans.

Those interim plans use available data and the results of changes to the grid connection process. They help operators decide which electricity network upgrades to proceed with in the 2030s while the National Energy System Operator (NESO) develops the wider plan.

NESO will also produce 11 regional energy plans in 2028 to show where local networks need investment. Nine cover regions in England, with one each for Scotland and Wales. These plans should help match local demand with decisions about major national infrastructure.

The challenge also involves grid connection and funding rules. Under Ofgem’s reforms, projects must show they are ready and needed to receive a confirmed electricity connection offer. The regulator also oversees network funding and is strengthening expectations for how quickly operators deliver connections.

Ofgem warns of the risk of inconsistent plans because interim electricity decisions come before the plan that shows where future power generation should go. For alternative energy developers, that means committing money while some of the information needed to judge network availability is still taking shape.

Hydrogen Adds a Costly Layer to the Puzzle

Producing hydrogen through electrolysis uses electricity to split water into hydrogen and oxygen. The gas then needs equipment for storage and transport. If a project uses that hydrogen to generate electricity later, the extra conversion causes further energy losses. Planners must account for the complete process when comparing hydrogen storage with batteries.

This full cycle loses 60% to 70% of the original electricity input, while batteries retain approximately 85% to 90% of it. These figures compare the energy put into each storage system with the electricity recovered afterwards. The losses vary with equipment and operating conditions.

Before committing to infrastructure, alternative energy planners need to establish how a project will use its hydrogen. Supplying hydrogen as a fuel involves different equipment and energy requirements from converting it back into electricity. Defining that use helps planners assess the electricity supply and facilities the project will need.

Households and Businesses Are Already Paying for the Gap

An electric vehicle (EV) charger can push demand beyond an existing electrical panel’s capacity. If a property has an outgrown electrical panel, an electrician can assess the additional load and determine whether an upgrade is necessary, particularly when existing equipment already causes frequent breaker trips.

The cost of remaining dependent on fossil fuels creates a separate concern. The Climate Change Committee reports that energy bill increases for households with gas boilers and petrol cars were almost four times as large as those for households with heat pumps and EVs. Its analysis covers increases since the start of the Iran war and illustrates the financial consequences of exposure to fossil fuel prices.

Businesses also need network access before they can electrify equipment. The committee calls for faster connections to enable industrial electrification and remove barriers to investment. Better coordination could help align the infrastructure businesses need with the timing of their projects. Households would also then gain a clearer basis for assessing the practical requirements of switching heating or transport.

Closing the Gap Before the Bills Add Up

Households and businesses must make investment decisions before the full plan arrives in 2028. Shared forecasts could help operators agree which network upgrades to prioritise. If those plans lead to coordinated investment, customers could have clearer information about available capacity and the likely costs and practical requirements of switching equipment.